Project Management
Interview
Interviewee: Cristen
Saline
Job Title: Software
Engineer
- Can you tell me about the last project you lead?
“The last project
I lead was called ESP. ESP is and ‘environment Service Pack’ that
includes many patches to the framework code that supports the Infor
ERP. This code affects the communication to many modules, like
external process flows. These patches are generally regulatory and
need to be implemented to conform to regulations.”
- What project management methodology did you use?
“Most projects
here use a Waterfall like method.”
- What skills did you acquired during the project?
“I learned to
better anticipate potential issues. I also have learned to better
anticipate my business user’s needs. Our business users do most of
the testing, while I am here to support and provide assistance when
needed.”
- How will you implement these skills in future projects?
“As I learn to
better foresee issues, I can mitigate risks and help the project to
be completed within the time restraints given.”
- How did you determine a realistic schedule for the project?
“Looking at past
projects really helped. Some of the similar projects I found had
estimated and actual times to them. Looking at these it was easy to
estimate the time it should take to complete a task, as always I
included a ‘buffer’ into the estimated time.”
- Explain your methods for resource allocation.
“Resource
allocation was built into the project, as we have business areas that
test their app area. For instance I have an HR resource. This HR
resource tests HR processes. Just like the schedule I used previous
projects to determine this resource schedule and tasks, while
incorporating new processes we have implemented after said previous
projects.”
- How do you inform all the stakeholders of the progress of the project on a regular basis?
“A weekly status
update is sent by the project manager to upper management and the
stakeholders. The project manager generally gets updates from me by
attending the meetings I hold or reading the minutes from those
meetings. I also send urgent updates to the project manager if needed
throughout the duration of the project.”
- How do you monitor risks to the project and mitigate them?
“Depends on the
risk. If the users that are testing the system come across issues it
is brought to the attention of the oversight committee. These risks
are then analyzed and classified from 1 – 5 risk level, 1 having
the most risk. Risks that are open on the Issues list are monitored
to mitigate them and a solution is usually produced. Sometimes there
are ‘Show-Stoppers’ which need to be resolved before the project
can go live. Another risk is staying within the time constraints
given to the project, this I directly affected by risks like the one
above. The time risk is hard to manage sometimes as I have to keep my
business users focused on the testing tasks and make sure tasks are
not held until the last day of testing.”
- What change management processes have you used to ensure that change is introduced properly?
“Phase 1 - Preparing for change
(Preparation, assessment and strategy development)
It really depends on the change, in my
current project there is a change to the employee portal. This has
been assessed and a strategy is being developed. Preparation is
generally figuring out the extent of the change. Assessment is where
we would bring the change to business users and they would assess
the effect this would have to their system. With our employee portal
the business users have assessed and believe that the change is ok.
Many of our users, Supply chain, AP, GL, Benefits were immediately
ok with the change, However HR has the most interest in this change
as it is their customers, the employees that are affected the most by
this change.
Phase 2 - Managing change (Detailed
planning and change management implementation)
For changes like this, where the
change will affect the whole of the employee population,
Communication is key. HR is beginning to develop a plan to
communicate this change to employees. I assume Emails and memos will
be sent to employees that do not have email. Onboarding and New
Employee Orientation will also be changed. The front line for this
change will probably be the support desk. Employees will call and
ask for help when this is implemented, the support desk will be
alerted and will develop procedures for helping the employees with
this change.
Phase 3 - Reinforcing change (Data
gathering, corrective action and recognition)
With this change there will be post
implementation processes, the support desk will log how many calls
they will get in regards to the change, if there were any outstanding
(low risk) issues they will be assessed and resolved as needed. As
well as time for any stabilization the system needs preformed.”
- What are the practices you follow for closing a project and meeting the conditions required to establish closure?
“When a project
is closing, we should already have signoff from the business users
that tested the project/changes, the stake holders will sign off,
assuming the requirements were met with satisfaction. The last thing
that takes place after a project has gone live is the lessons learned
meeting. I believe this is the best part of the project. This is
where I learn the most, whether or not I met the business user’s
expectations and how I can do better with the next project I lead.”
Project Management Interview
Interviewee: Carl Huskey
Job Title: Software
Engineer
- Can you tell me about the last project you lead?
"The last project I led was the
rewriting of a web form utilized by the entire company, to keep track
of the skills and qualifications of all employees."
- What project management methodology did you use?
“I used the
waterfall methodology, going through the phases the phases of:
Conception: management was informed that the existing form needed to
be fixed , Initiation: I looked at the current structure of the form
and fixed what I could but informed management that it will need to
be rewritten, Analysis: I then went out and spoke with different
leaders to see exactly what they would like the form to do and broke
up the requests into smaller parts, Design: after the requirements
were all gathered I came up with a design and project plan; creating
a project charter and having a kick off meeting, Construction: I then
wrote the web form, Testing: I had three system tests where I had the
users who presented requests for the form test it and give me
feedback which I took and implemented before the next testing phase,
Production/Implementation: the form was put up into production after
system test three changes had been made, and Maintenance: I have not
yet had to, but I am responsible should any need to be done. ”
- What skills did you acquired during the project?
“I learned how to manage users during
a system test, and how to entice them to sign up for system testing.
The key to getting them to sign up is reminding them that they do
care about the final product and if they would like to make sure
their suggestions make it into and are properly represented in the
final product they need to participate in the test phases. It is also
important to leave the test phases open for a long enough time that
everyone has a chance to get on and play with it; while at the same
time not giving them too much time that they put off the testing.”
- How will you implement these skills in future projects?
"I will know how to deal with the
users and keep them organized and focused during a testing period"
- How did you determine a realistic schedule for the project?
“I spoke with my mentor and other
team members taking advice on their thoughts on how user testing
would go, calculated the amount of time I thought it would take form
me to write out the code, and utilized Microsoft project to develop
my time line.”
- Explain your methods for resource allocation.
“The only allocation of resources was
which users I wanted to have test/users I had volunteer for testing.
I wrote the web form myself with little help from anyone else. ”
- How do you inform all the stakeholders of the progress of the project on a regular basis?
“I had a weekly update meeting with
my director in which we would discuss the overall project completion
and what part of the form I was currently working on. The other
stakeholder/the users were informed with the progress of the project
during each system test. They were able to actually see how the form
was working and what areas still needed to be ironed out.”
- How do you monitor risks to the project and mitigate them?
“There were no big risks in this
project, other than having the existing web form threaten to fail as
I worked on its replacement.”
- What change management processes have you used to ensure that change is introduced properly?
“I met with the group of users to
prepare them/inform them of the change that would be coming in the
way of the new form. I managed the change by following my project
plan, and I reinforced the change by gathering feedback from the
users during the system tests so by the time the project was complete
they were comfortable with the new form.”
- What are the practices you follow for closing a project and meeting the conditions required to establish closure?
“I went back to my project charter
and review what our definition of done was, made sure the project
meet that definition, and the users were happy with the new form.”