Sprint 4 Backlog, Tasks & Estimates

Sprint 4 will mainly be us clarifying and fixing any issues that arose w/ the first three sprints.

Backlog- 1. we will make changes to the Promoted Sitter slideshow (2 days)
                2.  We will revise the site reviews, and make sure that the words don't cut off right in the                               middle (1 week)
                3.  We will get the "thank you for signing up" emails to work, and customize them to look as                       close to the sketch as we can (2 weeks)

Tasks
1. Meet with clients (happening Monday the 14th) to discuss changes
2.  get changes written on paper, with new drawings done to finalize the designs.
3.  we will need to add more notification emails, and need more code from the client to be sure we're not working with outdated files.

and that's all folks....