Sprint 4 consists of us creating email functionality within the site and touching up the rest of the site.
Backlog:
1. Create email functionality within the site (1 week).
a) Get the picture to show up within the email (2 days)
b) Align the text of the message with the picture/background (2 days)
c) Make message work for all email domains (gmail/yahoo/cox/etc.) (3 days)
2. Touch up the website (1 week)
a) Write the project report (1 week)
3. Create message board within the site (3 weeks)
Tasks:
1. Meet with clients (happening Monday the 14th) to discuss changes
2. Get changes written on paper, with new drawings done to finalize the designs.
3. We will need to add more notification emails, and need more code
from the client to be sure we're not working with outdated files.